Guangxi Beihai Changli Tempering Furnace Production Line Noise Reduction Case Study


Project Overview

This industrial production line noise reduction project was completed for Changli Glass in Beihai, Guangxi. The continuous-running glass tempering furnace and supporting large fans produce severe aerodynamic noise and mechanical vibration noise, causing excessive noise in the workshop.

We provided a full tempering furnace acoustic enclosure solution, including modular sound insulation enclosure, ventilation acoustic louvers, internal sound absorption and vibration isolation treatment, ensuring stable production and effective noise control.


 


Noise Sources & Challenges

Main noise sources:

• Tempering furnace fan aerodynamic noise

• Mechanical vibration and pipeline airflow noise

• Indoor reverberation noise superposition

Key challenges: The acoustic enclosure must guarantee sufficient ventilation and heat dissipation for 24-hour continuous furnace operation. Reserved maintenance doors are required for daily equipment inspection and overhaul.


 


Custom Noise Reduction Solution

Modular Acoustic Enclosure

Heavy-duty composite sound insulation panels form a closed acoustic enclosure for the tempering furnace fan area. Fully sealed panel joints effectively block outward noise transmission.

Ventilation Acoustic Louvers & Silencers

Equipped with low-resistance acoustic louvers and exhaust silencers to ensure air circulation and heat dissipation while preventing noise leakage.

Sound Absorption & Vibration Isolation

Internal sound-absorbing materials reduce indoor reverberation. Fan base vibration isolators and flexible pipe connectors cut off structural vibration noise.


 


Key Specifications

• Noise reduction: 19–25dB(A), meets industrial workshop noise standards

• No impact on tempering furnace heat dissipation and production efficiency

• Dust-proof and durable structure for long-term factory operation

• Reserved acoustic maintenance doors for easy overhaul

• 


On-Site Installation

The integrated modular tempering furnace acoustic enclosure is installed along the production line. The overall structure is stable and tidy, realizing professional noise isolation without affecting normal production.


Project Results


• Effective noise control: Greatly reduces production line noise and improves workshop working environment.

• Stable production: Optimized ventilation design ensures long-term safe operation of tempering furnace.

• Durable performance: Industrial-grade acoustic structure adapts to glass factory working conditions.

• Easy maintenance: Reasonable reserved passages support daily equipment inspection.